When homeowners ask how long a kitchen remodel takes, they usually mean how long will my kitchen be unusable. Those are two very different numbers, and conflating them is the source of most remodeling frustration in Miami.
Construction is 6–10 weeks for a typical full kitchen remodel. The complete project — from first conversation to final inspection — is usually 4–7 months. The gap between those numbers is design, selections, permitting, and lead times, and almost all of it happens before a single cabinet comes out.
A full kitchen remodel in Miami takes 4–7 months end to end, broken into roughly 3–6 weeks of design and material selections, 4–10 weeks of Miami-Dade permitting, and 6–10 weeks of active construction. Your kitchen itself is out of service for the construction window only — typically 6–10 weeks. Cosmetic refreshes that do not move plumbing or electrical can skip permitting and finish in 2–3 weeks.
Source: Miami Pro Remodeling, licensed kitchen remodeling contractor serving Miami-Dade and Broward County, Florida.
Nothing gets built until every decision is made. That sounds obvious, and it is still where most schedules quietly lose a month.
This phase covers layout, a line-itemed scope, and — critically — final selections: cabinet door style and finish, countertop material and slab, backsplash tile, flooring, plumbing fixtures, appliance model numbers, hardware, and lighting. Appliance specs matter more than people expect, because cabinet shop drawings are built around exact appliance dimensions. A range swap after cabinets are ordered is an expensive mistake.
The clients who move fastest here are the ones who make decisions in batches rather than one at a time. The ones who stall are usually waiting to "see it in person" on every single item.
This is the phase Miami homeowners consistently underestimate, and it is largely outside any contractor’s control.
If your remodel moves plumbing, alters electrical circuits, or touches walls, you need a permit. Cosmetic replacement generally does not. The timeline depends heavily on jurisdiction — unincorporated Miami-Dade, the City of Miami, Coral Gables, Hialeah, and Miami Beach all run separate review processes at different speeds. Structural work, such as removing a load-bearing wall, adds engineering drawings and additional review.
Two practical notes. Permitting runs in parallel with cabinet lead time, so this is not purely additive to your schedule. And skipping permits to save six weeks is a false economy — unpermitted work surfaces during resale and can stall a closing. Our Miami-Dade permit guide covers the details.
Here is what the 6–10 week construction window actually looks like on a typical Miami kitchen:
| Week | Work | Notes |
|---|---|---|
| Week 1 | Protection, demolition, haul-off | Concealed conditions surface here — old cast iron, surprise wiring, hidden damage |
| Weeks 2–3 | Plumbing and electrical rough-in, framing changes | Rough-in inspections must pass before walls close |
| Week 3–4 | Drywall, plaster, prime | Humidity affects cure and dry times in South Florida |
| Week 4–5 | Flooring installation | Depends on material; tile needs cure time before cabinets |
| Week 5–6 | Cabinet installation | The visual turning point — the room finally reads as a kitchen |
| Week 6 | Countertop templating | Cannot happen until cabinets are set and level |
| Weeks 7–8 | Counters installed, backsplash tile, plumbing trim | Fabrication gap of 1–3 weeks after templating |
| Weeks 8–10 | Appliances, lighting, hardware, paint touch-up, final inspection | Punch list and final walkthrough |
The two moments that surprise people: weeks 2–4 feel like nothing is happening (rough-in and drywall are unglamorous), and the countertop gap after cabinets go in. Templating cannot occur until cabinets are installed and level, then the slab is fabricated. That 1–3 week wait is physics, not negligence — and during it you have cabinets with no counters, which feels worse than it is.
Miami kitchen remodels run long for four main reasons: (1) permitting, which varies by municipality and takes 4–10 weeks; (2) inspection scheduling, which pauses work until an inspector is available; (3) cabinet lead times of 3–8 weeks for semi-custom; and (4) concealed conditions in older homes — deteriorated cast-iron drain lines, undersized electrical service, and unpermitted prior work are common in Miami-Dade housing stock built before 1980.
Source: Miami Pro Remodeling, licensed remodeling contractor, Miami-Dade and Broward County, Florida.
Mid-project scope changes. The single largest controllable delay. Changing the backsplash after tile is ordered, or relocating a sink after rough-in, does not just cost money — it can reset an inspection sequence. Every change order is a schedule event.
Concealed conditions. Miami-Dade has enormous inventory of 1950s–1970s construction. When we open those walls we regularly find deteriorated cast-iron drain lines, undersized panels, and prior unpermitted work. Discovering it is not the problem; discovering it in week two of a schedule with no contingency is.
Inspection scheduling. Work stops until the inspector arrives. Nobody controls the queue.
Long-lead items. Semi-custom cabinets run 3–8 weeks. Specialty tile, imported stone, and panel-ready appliances can run longer. These get ordered during permitting for exactly this reason.
Most of our clients stay in the house. It is manageable with preparation.
Set up a temporary kitchen before demo: refrigerator relocated to a garage or dining room, microwave, coffee setup, paper goods, and access to a sink — usually a bathroom or laundry. Plan for dust despite containment; we seal work areas and run negative air, but Miami construction generates dust. Expect crews on site roughly 7:30am to 4pm on weekdays. If you work from home, plan around the noisy phases: demo, tile cutting, and cabinet installation.
Budget realistically for eating out during the countertop gap. It is the phase that tests patience most.
If speed is your priority: finalize all selections before permit submission so cabinets can be ordered immediately; choose in-stock or quick-ship cabinetry rather than custom; keep plumbing and electrical in their existing locations, which can eliminate the permit entirely on a cosmetic-only scope; and resist changes once work begins.
A refresh-level remodel — counters, backsplash, paint, hardware, lighting, no relocations — genuinely finishes in two to three weeks. If your layout works and only the finishes are dated, that path gets you a transformed kitchen before a permitted remodel would even break ground. Our Miami kitchen cost guide compares both paths.
Plan on 4–7 months total: 3–6 weeks design and selections, 4–10 weeks Miami-Dade permitting, and 6–10 weeks of construction. Construction alone is 6–10 weeks.
Typically 4–10 weeks depending on jurisdiction and whether structural work is involved. Unincorporated Miami-Dade and individual municipalities run on different timelines.
Most clients do. Expect 6–10 weeks without a functioning kitchen. We recommend setting up a temporary kitchen with a fridge, microwave, and sink access before demo begins.
Countertops are templated after cabinets are set, then fabricated. Templating to installation typically runs 1–3 weeks — the gap is unavoidable because the template must match installed cabinets exactly.
Permitting, inspection scheduling, cabinet lead times, and mid-project scope changes. Concealed conditions such as cast-iron drain lines or undersized electrical are common in older Miami homes.
Miami Pro Remodeling is a licensed, insured remodeling contractor serving Miami-Dade and Broward County. Every estimate we write is line-itemed, on-site, and free.